UPDATE: To complete reconstruction and expansion of the intersection at Falls Avenue West and Grandview Drive, the contractor will temporarily shift the existing north- and south-bound lanes to the east. The shift will allow workers to complete paving, curb, and sidewalk on the west side of the intersection.
Grandview Drive will remain open and Falls Avenue West, west of Grandview Drive, will remain closed for about 1,000 ft. until completion of the project. Work is expected to be completed by September 30.
Drivers should use North College Road West to access Falls Avenue West, Sunway Soccer Complex and N 2700 E.
---
The schedule for reconstructing Falls Avenue West, west of Grandview Drive, will be extended to include the remaining work for reconstruction of Falls Ave West. The initial completion date of May 3 will be extended through September 30, so that contractors can complete the additional work without requiring additional road closures.
Falls Avenue West between Grandview Drive and 1280 Falls Avenue will remain closed to all traffic while this project is ongoing. And a section of the west shoulder of Grandview Drive North near the Falls Avenue intersection will also be under construction to expand Grandview Drive to the full road width.
Drivers should use North College Road West to access Falls Avenue West and Sunway Soccer Complex as well as N 2700 E. Questions about this project should be directed to Extreme Excavation at 208-544-7625.